Central Counties Cooperative Gas Station Under Construction

A major project is in the works at Central Counties Cooperative in Litchfield. The old fuel tanks are being removed and new ones should be installed at the Cenex c-store within 6-to-8 weeks.
General Manager Justin Schroeder says two pumps are gone already and the full project will begin on Monday. He says temporary pumps will be set up on the east side of the complex.
Schroeder says the project will take 6-to-8 weeks as it will take time for the concrete to cure in stages. He says when it’s all done, one of the items they will be adding is E15.