Highway 15 Resurfacing Project
A Minnesota Department of Transportation resurfacing project on Highway 15 from Dassel to Kimball gets underway on Monday, July 10th. Work is scheduled to be completed by October 6th but the start and end dates could change due to weather and other unforeseeable circumstances.
A detour is required to complete the project. The detour of Highway 15 begins July 10th and is scheduled to be in place for the project’s duration. Traffic will be routed on Highway 12, Wright County Road 3, and Highway 55.
MnDOT is resurfacing Highway 15 from the intersection of Highway 12 in Dassel to the Meeker/Stearns County line near Kimball. Guardrail near the Kingston bridge will be replaced as part of the project. Also – 30 culverts will be lined along the project area and three culverts will be replaced. A chip seal will be applied to the new pavement in early summer 2024.
Duininck, Inc., is the project contractor and the cost is $11.5 million.